The District is a local government agency and follows The Utah Procurement Code, as amended.  Current procurement needs and requests will be advertised below.

Current Procurement Announcements:

Mountain Regional Water Special Service District’s 2025 Pre Qualified Vendor List for Engineering Service Providers  

 

August 6, 2026 - 

ADVERTISEMENT FOR BIDS AND LEGAL NOTICE - For procurement of Electrical Distribution Equipment related to the Signal Hill Treatment Plant Optimization Project.  Specs and Contract document can be found in the document linked below.

Mountain Regional Water - Contract/Technical Specs - Electrical Equipment Procurement

 

-July 20, 2026

The Mountain Regional Water Special Service District (District) will accept Statements of Qualification (SOQ) from qualified and licensed General Contractors and Electrical Contractors interested in bidding on the Signal Hill Water Treatment Plant Optimization Project. Project construction bids will only be accepted from those Contractors who have been pre-qualified by the District. No other General Contractors or Electrical Contractors will be eligible to bid on this Project. The intent of this solicitation is to obtain SOQs from General and Electrical Contractors and to pre-qualify bidders for this work. The District intends to pre-qualify electrical subcontractors or electricians who will also be required to prepare and submit a similar SOQ to the District. This document sets forth the minimum acceptable requirements for SOQs from General Contractors and Electrical Contractors, hereafter referred to as Contractors.  See full document below.

Mountain Regional Water - Signal Hill Treatment Plant Optimization Project 
General & Electrical Contractor Request for Statement of Qualifications


 

REVISED-Bid Package-OldRanchWell - 19Jan2026.pdf

     Revisions include:

  • DOCUMENT 00400 – BID, the following sections have been modified
    • Part 3, Price Schedules, the following pay items have been added:
      • Item 13 – Transport Development Water to Offsite Location
      • Item 16 - Obtain and Comply with all Monitoring and Reporting Requirements of a UPDES General Permit for CDHT
      • Item 19 - Furnish and Install Artesian Well Head
    • Part 5, Measurement and Payment, the following descriptions have been added:

§  5.15     Transport Development Water to Offsite Location (Bid Item 13)

§  5.18     Obtain and Comply With All Monitoring and Reporting Requirements of a UPDES GeneraL Permit For CDHT (Bid Item 16)

§  5.21     Furnish and Install Artesian Well Head (Bid Item 19)

 

  • TECHNICAL SPECIFICATIONS, the following sections have been modified
    • Section 1.12, MANAGEMENT OF DRILL CUTTINGS, DRILLING FLUIDS AND PRODUCED WATER
    • Section 3.18 – WELL CAP CONSTRUCTION FOR NON-ARTESIAN CONDITIONS
    • Section 3.19 – WELL CAP CONSTRUCTION FOR ARTESIAN CONDITIONS

 

Dates and other requirements remain unchanged.